The Challenge:
The Ashfield District Council has put out a request for proposals for a project that would involve modifying a semi-detached property to accommodate people with disabilities and adding a single-story back extension. The council was on a mission to find a skilled builder who could finish the project according to standards and within budget, as it was under pressure from outside agencies to provide accommodations for disabled people by a certain date. British Builders was chosen by Ashfield Council because of our proven ability to complete projects on time and under budget.
The Solution:
Two teams cooperated in order to expedite the process without compromising quality or safety in order to meet the council’s strict budget and deadline. The second group worked evenings and weekends to expedite the process. In addition, in order to prevent work interruptions and delays, all materials and equipment had to be delivered to the project site prior to its commencement. The work consisted of:
Preparation: Scaffold was erected, waste skips parked, material delivered and stored safely, CCTV put in operation. Welfare facilities installed onsite and H&S signages installed where appropriate.
Demolition: Complete strip out of the existing kitchen and bathroom, including base units, service pipework, radiators, wall tiling, windows & doors with frames, lintels, outbuilding, kitchen’s internal walls. Partial demolition of the external rear wall and a strip out of the roof and its associated cladding to provide an opening into the proposed extension.
Drainage: Removed all existing interconnected sanitary sewer systems, constructed new rain drainage, sewage systems with inspection chambers.
Construction of the foundations and platforms (for the extension): The trench foundation was excavated and poured with concrete, solid floor was constructed in accordance with the council’s plan specifications
External and Internal walls: New cavity walls have been constructed and bonded to the walls of the bathroom and kitchen. A U-shaped steel beam was installed to enlarge the doorway to the wet room, bedroom 2, and kitchen. Proposed Wet room/kitchen/bedroom/hall walls constructed of wood studs and mineral wool insulation
Roof: The flat roof was constructed using Sika damp-proofing technology Per SIKA specifications, with a 20-year insurance-backed warranty that includes downspouts and gutters
Windows & Doors: New UPVC windows and internal timber doors were installed with all other associated jobs
Electric work: Our certified electricians have completed a full rewire of the property, including the installation of new lighting and outlets, consumer unit, switches as per the specification’s requirements.
Plumbing/heating: Installed new gas piping, repositioned the existing combi boiler, supplied and installed new radiators in the kitchen.
Kitchen and Bathroom units: Installed new kitchen, and bathroom units including a wheelchair-accessible toilet
Decoration: Carried out interior tiling, plastering and decoration including woodwork
Access Ramp: Built new access ramp with handrails in front of the main door
Drive: Before tarmac work, we excavated the ground to 300mm below the surface, completed curbing, protection, layering then installed block paving and sandstone sets and finally carried out tarmacing work
Completion:
The entire project was completed with the approval of building control and the Ashfield District Council, and it was successful in every way